Supply & Installation of 66kV Power Cables, Auxiliary Cables and Accessories
PROJECT DESCRIPTION:
-
SP Group 66kV EHV Cable EPC Project Supply, Install, Commissioning of Route E Crawford Substation to Marina Center Substation & Route B from Upper Jurong to Gul Channel including cable pulling work, cable jointing work & all necessary cable testing work for Singapore Power Grid
SCOPE OF WORK:
Engineering Design, Procurement & Construction & Commissioning:
-
Design of 66kV XLPE EHV Cable structure, cable trench details, joint bay construction details
-
Supply of 66kV XLPE EHV Cable and EHV Cable joint and termination
-
Cable pulling work, Cable jointing work & Cable termination work
-
Commissioning of entire cable system according to SP Group standard
-
Management of subcontractors
CLIENT: SP Group LOCATION: SINGAPORE
DURATION: 2019-2021