TYPICAL PROJECT
Combined Cycled Co-Generation Plant of Beijing Environmental Improvement Project




PROJECT DESCRIPTION

  • Beijing Zhengdong Combined Cycle Co-generation Power Plant (PN-1) (2+2+1) is built to supply electricity, water and steam for Beijing Electronic Zone under financing from JIBC.


SCOPE OF WORK

  • Engineering Design,
  • Procurement,
  • Construction,
  • Test and Commissioning of 2+2+1 Combined Cycle Plant.


CLIENT:  Beijing Zhengdong Group              LOCATION: Beijing,China

DURATION: 2002-2004


  • Next:No more